Infrastructure
Status: Completed
Ref: CP 726/5
Drainage of Existing Fish Market at Abu Hamour- Development - CP 726/5
Client / Employer
PWA—Infrastructure Affairs (Drainage)
Status
Completed
Date Started
October 2, 2012
Completion Date
June 2, 2016
Contract Value
QAR 28.3 Million
Project Scope & Specifications
Foul and storm water drainage system of the existing Fish market and construction of Membrane Bioreactor (MBR) package treatment plant.
Project Engineering & Stakeholder Partners
Project Management Consultant (PMC): Parsons Brinckerhoff (PB)
General Engineering Consultant (GEC): Parsons Int'l. Ltd. (PIL)