Infrastructure
Status: Ongoing
Ref: MH001
C2024-8 Rectification of Settlements/Subsidence Around Manholes and Associated Works at Various Locations
Client / Employer
Public Works Authority
Status
Ongoing
Date Started
June 9, 2024
Consultant
Italconsult
Contract Value
QAR 23.07 Million
Project Scope & Specifications
The scope of woks consists of the excavation and disposal of existing backfill material and refill with foam concrete and roads reinstatement to bring back the surface to their original proposed condition, as consequent to the settlement occurred in the backfill of deep micro tunnelling shafts constructed under projects DN117-P01, DN107-P03 and DN107-P05 constructed by another contractor.